Enemalta 2027 distribution investment programme
Around €75 million is announced for electricity-distribution investment in 2027.
Approximately €75 million in 2027
Infrastructure / capacity—not a cash benefit.
Speech printed p. 58 · PDF p. 62
Budget 2027 · Chapter 6
Separate completed network works, new investment programmes, study-stage projects and renewable-energy targets.
Around €75 million is announced for 2027 electricity distribution. This is a programme figure, not an allocation to every project named nearby. The process for two 33kV submarine cables between Malta and Gozo has been launched; a separate 132kV connection is at technical-study stage. Historical substations and cable works should not be counted again as new 2027 investment.
Around €75 million is announced for electricity-distribution investment in 2027.
Approximately €75 million in 2027
Infrastructure / capacity—not a cash benefit.
Speech printed p. 58 · PDF p. 62
Enemalta has launched the process for adding two 33kV electricity cables under the sea between Malta and Gozo.
2 submarine cables, 33kV
Infrastructure / capacity—not a cash benefit.
Speech printed p. 58 · PDF p. 62
Technical studies cover a new 132kV connection between Malta and Gozo.
132kV proposed connection
Infrastructure / capacity—not a cash benefit.
Speech printed p. 58 · PDF p. 62
The speech reports 208 completed substations, over 270 km of cables and completed distribution centres in Naxxar, Siġġiewi and Msida.
208 substations; 270+ km of cables; €9m Msida centre (historical)
Infrastructure / capacity—not a cash benefit.
Speech printed p. 58 · PDF p. 62
The second Sicily interconnector is described as doubling interconnection capacity. Technical studies continue for a third interconnector, while first offshore-wind-farm studies envisage 300 MW. These capacities and study stages must not be confused with commissioned equipment or confirmed completion dates. Renewable imports from North Africa are an exploration direction, not a signed supply contract.
The second interconnector with Sicily is expected to double Malta's interconnection capacity.
Infrastructure / capacity—not a cash benefit.
Speech printed p. 58 · PDF p. 62
Technical studies are under way for a third interconnector.
Infrastructure / capacity—not a cash benefit.
Speech printed p. 58 · PDF p. 62
Studies continue for a first offshore wind farm with envisaged capacity of 300 MW.
300 MW envisaged capacity
Infrastructure / capacity—not a cash benefit.
Speech printed p. 58 · PDF p. 62
Opportunities to import renewable energy from North Africa are being explored.
Direction of policy; no individual entitlement implied.
Speech printed p. 58 · PDF p. 62
The speech calls for large-scale battery investment and more domestic battery opportunities, but gives no new household grant amount or storage capacity. It states a 25.0% renewable-energy target for 2030 and reports 18.8% in 2025. The general scheme-renewal announcement includes renewables and electric vehicles; individual eligibility and amounts still require scheme notices.
The government plans further investment in large-scale batteries and more opportunities for domestic batteries.
Direction of policy; no individual entitlement implied.
Speech printed p. 59 · PDF p. 63
The speech states a target of 25.0% of energy from renewable sources by 2030, against a reported 18.8% share in 2025.
25.0% target by 2030
Forecast or target—not a guaranteed outcome.
Speech printed p. 59 · PDF p. 63
The speech announces renewal of existing schemes, including housing, home buying and restoration, NGOs, sport, electric vehicles and renewable energy.
Renewal announcement; scheme-specific terms need verification.
Speech printed p. 56 · PDF p. 60
More recurrent and capital funding is directed towards Maltese landscapes, maintaining existing recreation areas and renewing neglected spaces.
Direction of policy; no individual entitlement implied.
Speech printed p. 60 · PDF p. 64
Budgets and dates not stated in the speech remain unfilled. Capacity figures describe planned facilities, not cash entitlements.
Process launched for two additional 33kV submarine cablesCompletion: Not stated
2027 distribution investment programme announcedCompletion: Not stated
Second interconnector described as doubling interconnection capacityCompletion: Not stated
Technical studies under wayCompletion: Not stated
Technical studies under way for a 132kV linkCompletion: Not stated
Feasibility studies continue; envisaged 300 MW capacityCompletion: Not stated